Question: During a project closing, problems with readiness or impact are evaluated. Which of the following project issues is an issue with readiness? A.) Picnic tables

During a project closing, problems with readiness or impact are evaluated. Which of the following project issues is an issue with readiness? A.) Picnic tables for the pavilions need to be delivered and installed. B.) Local groups thought the park would include a shelter that could be reserved for events. C.) Some citizens are upset that historic buildings were demolished to build the new green space. D.) Some stakeholders feel having a playground in the park is dangerous