Question: During a project, earned value analysis is performed, resulting in the following numbers: EV: 523,000; PV: 623,000; AC: 643,000. Which results are correct? Select one:
During a project, earned value analysis is performed, resulting in the following numbers:
EV: 523,000; PV: 623,000; AC: 643,000. Which results are correct?
Select one:
a.
CV: -100,000; SV: -120,000
b.
CV: +120,000; SV: +100,000
c.
CV: +100,000; SV: +120,000
d.
CV: -120,000; SV: -100,000