Question: During a project's execution, unexpected issues can arise, leading to changes in project requirements. Project coordinators need to follow a standard process to manage these

During a project's execution, unexpected issues can arise, leading to changes in project requirements. Project coordinators need to follow a standard process to manage these changes effectively. The formal proposal that you create to request these modifications from the client is called a *__________*. Question 1 options: Change plan Change log Change request Change order