Question: During a Sprint, a Development Team determines that it will not be able to finish the complete forecast. Who should be present to review and
During a Sprint, a Development Team determines that it will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected? Group of answer choices The Scrum Master, the project manager, and the Development Team The Product Owner and the Development Team The Product Owner and all stakeholders The Development Team