Question: During a testing phase for Project called A. At the end the team manage to deliver the Project A one week early. After three weeks,
During a testing phase for Project called A. At the end the team manage to deliver the Project A one week early. After three weeks, the user of Project A claimed they found 13 errors. Before your team deliver the Project A, they found 406 errors during the testing task. What is the defect removal efficiency for the Project-A?