Question: During August, Leming Inc. worked on two jobs. Data relating to these two jobs follow: Job 64 Job 65 Units in each order 50 80

During August, Leming Inc. worked on two jobs. Data relating to these two jobs follow:

Job 64

Job 65

Units in each order 50 80
Units sold 50 --
Materials requisitioned $3,560 $785
Direct labor hours 410 583
Direct labor cost $6,720 $9,328

Overhead is assigned on the basis of direct labor hours at a rate of $11. During August, Job 64 was completed and transferred to Finished Goods. Job 65 was the only unfinished job at the end of the month.

Required:
1. Calculate the per-unit cost of Job 64.
2. Compute the ending balance in the work-in-process account.
3. Prepare the Aug. 31 journal entries reflecting the completion and sale on account of Job 64. The selling price is 175% of cost. Refer to the chart of accounts for account titles. Round all journal entry amounts to the nearest dollar.

1. Calculate the per-unit cost of Job 64.

The per-unit cost of Job 64 is .

2. Compute the ending balance in the work-in-process account.

The ending balance in the work-in-process account is .

3. Prepare the Aug. 31 journal entries reflecting the completion and sale on account of Job 64. The selling price is 175% of cost. Refer to the Chart of Accounts for the exact wording of account titles. Round all journal entry amounts to the nearest dollar.

PAGE 1

GENERAL JOURNAL

DATE ACCOUNT POST. REF. DEBIT CREDIT

1

2

3

4

5

6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!