Question: During planning. The team has identified the items in the following table as work to be done on the project. Draw a network diagram to

  1. During planning. The team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships, and duration is in days.

 

Duration

Predecessor

A

1

Start

B

2

A

C

4

B

D

2

B

E

3

B

F

4

D

G

6

F

H

1

E

I

5

H

J

2

C

K

1

G,I,J


If task F change from F-S relationship to S-S relationship with Task D. What is the critical path?

If task F change from F-S relationship to F-F relationship with Task D. What is the critical duration?

What is the Critical Path?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

well first need to const... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Computer Network Questions!