Question: During schedule and cost control, when comparing performance to the schedule and cost baselines, if schedule or budget has changed these changes should be: a
During schedule and cost control, when comparing performance to the schedule and cost baselines, if schedule or budget has changed these changes should be:
a added to the original baselines, and baseline changes made to reflect the new status
b formally recommended and managed through the integrated change control system
c reviewed with the customer or sponsor to obtain approval for additional funding
d implemented immediately and reported as variances from baseline in the next status report