Question: During schedule and cost control, when comparing performance to the schedule and cost baselines, if schedule or budget has changed these changes should be: a

During schedule and cost control, when comparing performance to the schedule and cost baselines, if schedule or budget has changed these changes should be:
a. added to the original baselines, and baseline changes made to reflect the new status
b. formally recommended and managed through the integrated change control system
c. reviewed with the customer or sponsor to obtain approval for additional funding
d. implemented immediately and reported as variances from baseline in the next status report