Question: During the management review and problem - solving meeting, one team raises the risk of not finishing a Feature beforethe end of the PI .

During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature beforethe end of the PI. How can the management team help ensure they complete the Feature within the PI?ROAM the risk appropriatelyRedefine the definition of done (DoD)Negotiate a reduction in the scopeUse buffer resources as a guard band