 During the most recent month at Jaster Corporation, queue time was

During the most recent month at Jaster Corporation, queue time was 25 days, inspection time was 0.4 days, process time was 0.75 days, wait time was 5.5 days, and move time was 0.35 days Required a Compute the throughput time. b. Compute the manufacturing cycle efficiency (MCE) c Compute the delivery cycle time