Question: During the P 2 V process, Hot and Cold, require all the similar steps except : Question 3 3 options: Determine the resources being used
During the PV process, Hot and Cold, require all the similar steps except :
Question options:
Determine the resources being used by the existing server to correctly size the necessary resources for the virtual machine.
Complete upgrade of the operating to the newer version and all software components
Create the virtual machine with the correct configuration.
Copy the data from the source physical server to the target virtual server.
Run postconversion cleanup and configuration.