Question: During the planning process in a matrix organization, the project manager determines the need for additional team members. Once a desired team member has been

During the planning process in a matrix organization, the project manager determines the need for additional team members. Once a desired team member has been identified, who would the PM request ask to have the desired person join the team?
Human resources
The project sponsor
The persons functional manager
The project team