Question: During the planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram

During the planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram to depict this flow, all relationships are F - S relationships and durations are in days Duration Predecessor

Duration Predecessor
A 1 Start
B 2 A
C 4 B
D 2 B
E 3 B
F 4 D
G 6 F
H 1 E
I 5 H
J 2 C
K 1 G, I, J

If task F changes relationhsip from F - S to F - F relationship with task D What is the critical path duration

If task F changes relationhsip from F - S to S - S relationship with task D What is the critical path duration

Need an answer in an hour, I will definitely upvote if I get an answer sooner

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!