Question: During the planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram
During the planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram to depict this flow, all relationships are F - S relationships and durations are in days Duration Predecessor
| Duration | Predecessor | |
| A | 1 | Start |
| B | 2 | A |
| C | 4 | B |
| D | 2 | B |
| E | 3 | B |
| F | 4 | D |
| G | 6 | F |
| H | 1 | E |
| I | 5 | H |
| J | 2 | C |
| K | 1 | G, I, J |
If task F changes relationhsip from F - S to F - F relationship with task D What is the critical path duration
If task F changes relationhsip from F - S to S - S relationship with task D What is the critical path duration
Need an answer in an hour, I will definitely upvote if I get an answer sooner
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock