Question: During the process of making a decision tree for a project, Federico set up the payoff matrix below. The payoffs would occur three years from

During the process of making a decision tree for a project, Federico set up the payoff matrix below. The payoffs would occur three years from today. The project is expected to cost $200,000 today. If the discount rate is 11%, what is the project's NPV? Multiple Choice $370,329 $570,329 $780,000 $580,000 $580,000