Question: During the procurement planning, the PM noted that he can run in a situation when the needed seller project members are not available to meet
During the procurement planning, the PM noted that he can run in a situation when the needed seller project members are not available to meet the schedule. This observation is: Valuable. He needs to complain to the Vice President of Human Resources in advance. Risk identification. He should include it in the procurement risk register Not important. He should disregard it. Not necessary. He will deal with it when the time comes