Question: During the risk management planning process for a software development project, a project team identifies a high - risk item related to the integration of
During the risk management planning process for a software development project, a project team identifies a highrisk item related to the integration of a new thirdparty tool into the system. The team has identified a contingency plan, but it is expensive and may impact the project budget.
What should the project manager do next?
Question options:
Ignore the highrisk item since there is a contingency plan in place.
Evaluate the costbenefit analysis of the contingency plan before implementing it
Wait and see if the risk materializes before taking any action.
Implement the contingency plan immediately to avoid any potential risks.