Question: During user testing, a client agrees to the final product. One day later, the client indicates that the final product may not be acceptable. What

During user testing, a client agrees to the final product. One day later, the client indicates that the final product may not be acceptable. What should be the project managers first step for resolving this issue?
Group of answer choices
Refer to the project charter and lessons learned register.
Review the projects requirements documentation.
Review the project's quality management plan.
Discuss concerns with the client and consult the projects acceptance criteria.