Question: during which team development stage is the team most resistant to adding new team members and any conflict considered averse? A Storming B Forming C
-
during which team development stage is the team most resistant to adding new team members and any conflict considered averse?
-
A
Storming
-
B
Forming
-
C
Performing
-
D
Norming
-
-
_____ is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.
-
A
Project management
-
B
Processes
-
C
Program management
-
D
Project life cycle
-