Question: Duting 2023 , Sheridan Comparyy started a construction job with a contract price of $1,760,000. The job was completed in 2025 . The following information
Duting 2023 , Sheridan Comparyy started a construction job with a contract price of $1,760,000. The job was completed in 2025 . The following information is wailable The contract is nan-cancellable (a) Calculate the amount of gross proft to be recognized each year, assuming the percentage-of-completion method is vsed. (Inter negative amounts using elther a negative sign preceding the number eg. 45 or parentheses es. (45)]
Step by Step Solution
There are 3 Steps involved in it
PercentageofCompletion Method Gross Profit Calculation Given Data Contract price 1760000 Costs incurred to date 2023 440000 2024 907500 2025 1177000 E... View full answer