Question: e . ( 3 points ) Use the resource leveling function of MS Project to find the resource constrained project du - ration and critical
e points
Use the resource leveling function of MS Project to find the resource constrained project du
ration and critical path. Assign Priority based on minimum slack time among tasks shared
by resource Core Team. Repeat the same for resource UI Team. Use the Standard tiebreaker
and include your solution in the Word document.
f points
Consider the shortest of the three project durations found in parts c through e Is this
schedule optimal for the resourceconstrained project? There are three possible answers:
YesNo and We cannot know from the available information Choose one of these
answers, and briefly explain and justify it