Question: e . ( 3 points ) Use the resource leveling function of MS Project to find the resource constrained project du - ration and critical

e.(3 points)
Use the resource leveling function of MS Project to find the resource constrained project du-
ration and critical path. Assign Priority based on minimum slack time among tasks shared
by resource Core Team. Repeat the same for resource UI Team. Use the Standard tiebreaker
and include your solution in the Word document.
f.(4 points)
Consider the shortest of the three project durations found in parts c through e. Is this
schedule optimal for the resource-constrained project? There are three possible answers:
Yes,No, and We cannot know from the available information. Choose one of these
answers, and briefly explain and justify it

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!