Question: e ) Assume the process is allowed to run for 1 hour. How many flow units can fully complete the process in this hour? A

e) Assume the process is allowed to run for 1 hour. How many flow units can fully complete the process in this hour? A flow unit is only considered to have fully completed the process if it enters and exits within this hour. - Please show your answer using a Gantt Chart (5 marks)
 e) Assume the process is allowed to run for 1 hour.