Question: E F G Project Activities and Costs (Normal vs. Crashed) Normal Crashed Activity Duration Cost (in U.S. Duration Cost (in U.S. dollan) dollar) A 4

E F G Project Activities and Costs (Normal vs. Crashed) Normal Crashed Activity Duration Cost (in U.S. Duration Cost (in U.S. dollan) dollar) A 4 days 1.000 3 days 2,000 B 6 days 1,800 3 days 3,000 C 4 days 2.500 3 days 4,000 D 9 days 2,700 6 days 6,500 E 8 days 2.400 6 days 4,500 5 days 3,500 3 days 7,000 G 2 days 2.400 1 day 3,000 Total costs $16 300 $30.000 Crashing Cost Activity Crashing Costs per Day (S) On Critical Path? 1.000 Yes 400 Yes 1,500 No 1,267 Yes 1,050 No 1.750 Yes 600 Yes
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
