Question: e following to answer questions 2 8 - 2 9 : A quality analyst wants to construct control charts for controlling a packaging process. Each

e following to answer questions 28-29:
A quality analyst wants to construct control charts for controlling a packaging process. Each day last week, he randomly selected four packages and weighed them. The data from that activity appears below.
Weight
Day
Monday
Tuesday
Wednesday
Thursday
Friday
Package 1
23
23
21
18
22
Package 2
22
21
19
20
18
Package 3
24
21
19
19
22
Package 4
23
18
22
19
20
The upper and lower control limits for the means are:
A) UCL =22.64; LCL =18.56
B) UCL =22.88; LCL =18.51
C) UCL =23.033; LCL =18.367
D) UCL =21.0; LCL =17.0
E) UCL =22.98; LCL =18.02
5 points
QUESTION 29
29. The upper and lower control limits for the Range are:
A) UCL =6.846; LCL =0
B) UCL =7.25; LCL =-5.2
C) UCL =7.759; LCL =0
D) UCL =6.389; LCL =0.0
E) UCL =7.302; LCL =0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!