Question: E = P + O + 4 M 6 A team is estimating the cost to build a brick wall. The worst case is estimated

E=P+O+4M6
A team is estimating the cost to build a brick wall. The worst case is estimated to cost $100, best case $70, most likely is $89.
Calculate the estimated cost.
a.89.33
b. $86.33
c. $87.79
d. $87.67
 E=P+O+4M6 A team is estimating the cost to build a brick