Question: e) Using the standard normal table the probability that the project will be finished in 70 days is (enter as a probability and round your

e) Using the standard normal table thee) Using the standard normal table thee) Using the standard normal table the

e) Using the

standard normal table

the probability that the project will be finished in 70 days is

(enter as a probability and round your response to three decimal places).

f) The probability that the project will be finished in 80 days is

(enter as a probability and round your response to three decimal places).

g) The probability that the project will be finished in 90 days is

(enter as a probability and round your response to three decimal places).

i More Info Time (days) Immediate Predecessor(s) a m b Activity A 8 12 10 7 B 6 9 3 3 4 C D 10 6 20 7 E 30 8 11 10 F 9 G 6 10 7 15 11 14 10 16 13 A B, D, E B, D, E F F G H I, J G H 6 7 8 4 7 8 K L 2 4 Print Done b) Determine the expected times and variances for each activity. (Enter your responses for expected times rounded to one decimal place and for variances rounded to two decimal places.) a m b Variance Activity A 8 10 7 12 9 Expected Time 10.0 7.2 3.2 B 6 0.44 0.25 0.03 3 3 4 D 10 20 30 20 11.11 E 6 7 8 7 0.11 F 9 10 11 10 0.11 6 7 G H 10 16 14 15 11 7.3 15.0 11.2 0.44 0.11 0.25 10 13 J 6 7 8 7 0.11 K 4 7 8 6.67 0.44 L 1 2 4 2.17 0.25 c) Determine ES, EF, LS, LF, and slack for each activity. (Enter your responses rounded to one decimal place.) ES EF LS LF Slack Activity A B 0.0 0.0 10.0 7.2 0.0 22.8 10.0 30.0 0.0 22.8 0.0 3.2 19.8 23.0 19.8 D E F G 47.7 H 30.0 40.0 40.0 37.3 55.0 51.2 40.0 50.8 55.0 55.0 62.0 17.7 0.0 10.8 K L

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!