Question: Each job j is desired to complete processing before its due date dj . The tardiness of a job j is defined as max (

Each job j is desired to complete processing before its due date dj. The tardiness of a job j is defined as max(0,Cj - dj)
The objective is to minimize the total tardiness
j 1234567891011121314151617181920
pj 1611419220512203201992291116110
dj 10072835584997171567487966077557195755162
Example on 5 jobs
j 12345 j 12345
pj 32555 Completion time Cj 35101520
dj 951076 Tardiness 000814
Time 01234567891011121314151617181920
Machine 12345
The total tardiness of this solution is equal to 22