Question: Each team will create a design / build project schedule for this project to be completed using accelerated design / construction principles. Tasks will be

Each team will create a design/build project schedule for this project to be completed
using accelerated design/construction principles. Tasks will be designated for each phase
of the project.
Engineering Tasks will include (but are not limited to):
1. Evaluation of the existing structure
2. Environmental assessment
3. Design of the renovations to existing pier
4. Design of the pier extension (to include structural, geotechnical, and hydraulic design)
Note: Each of these tasks will contain multiple sub-tasks
Construction Tasks will include (but are not limited to):
1. Demolition of existing facilities
2. Renovation of existing pier
3. Construction of new pier
Note: Each of these tasks will contain multiple sub-tasks
Project Management Considerations/Tasks will include (but are not limited to):
1. Permitting
2. Liaison with relevant governmental agencies (local, state, and federal)
3. Staging of materials
4. Impact on other beach activities / businesses during construction
5. Interaction between design and build principals
6. Removal of debris
7. Inspections
8. Opening to Public
You do not have to give specific dates or lengths of time. I am interested to see how you will
arrange the tasks in your schedule to allow you to complete the project in the shortest amount
of time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!