Question: Early Start Duration Early Fish Stack Late F Note: The project starts on Day 0: activities A and H start from 0 1- Draw

Early Start Duration Early Fish Stack Late F Note: The project starts on Day "0": activities "A" and "H" start from 0 1- Draw the Gantt chart based on the information that we can extract from the diagram above. 2- Perform a Forward and Backward Pass of the diagram above 3- identify the critical path(s) 4- If we remove activity J, and link activity I to K. identify the critical path and the Slack time for earch activity