Question: Earn Value Analysis 1. Complete the table O All cells must be completed. o All activities should have EAC number. . Open a Word file

Earn Value Analysis 1. Complete the table O All cells must be completed. o All activities should have EAC number. . Open a Word file and answer the following questions: 1. Explain what method used to calculate the indicators (in case of those who have more than one way to calculate) 2 How much more fund do this project would need at the time of completion? Why? 3. Can some adjustment to cost performance of the project be done in order to finish it as originally planned? Explain BCN5626 - EVM Assignment Table - Please fill all empty cells. Planned Actual Over Behind ID Activity Name Progress Progress DA BAC/BCAC PV/BCWS EV/BCWP |AC/ACWP (S) is (S ) VAC (S) TCPI budget? Schedule ? (9%) ($) ($) (%) (Yes or No) (Yes or No) 1 Clearing & grubbing 100% 100% 10,000 13,000 2 Excavation & Hauling 100% 80% 20,000 14,000 3 Drainage System 40% 60% 50,000 36.000 4 Fine Graveling 10% 0% 20,000 Pavement 0% 0% 25,000 5,000 6 Guard & Signs 0% 15% 10,000 2,000 Project Total The owners have decided to agree with a "certain amount of raise" in Estimate at Completion, since they are convinced that the contractor can reach the new EAC with only 8% increase over current (cost) performance. Calculate the amount of raise
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
