Question: Earned Value 2. A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of

Earned Value

Earned Value 2. A sales project at month 5 had an

2. A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI