Question: Earned Value Analysis A contractor has established the following earned value figures for concrete work: $ 2 . 1 0 ? sf of formwork $

Earned Value Analysis
A contractor has established the following earned value figures for concrete work:
$2.10? sf of formwork
$62.00? cy of concrete placed
$0.70lb of rebar set
The contractor is evaluating a subnetwork consisting of his concrete operations as part of a larger
project. The subnetwork contains forming, rebar setting, and concrete and curing activities.
Forming and rebar are estimated to take 2 weeks overall followed by 1 week for concrete and
cure activities. Estimated quantities are 10,000 sf of formwork, 12,000 lbs of rebar and 150cy of
concrete.
Three weeks have passed since the start of this subnetwork. The following weekly report
provides the job status.
Analyze the status of this subnetwork regarding budget and schedule.
Earned Value Analysis A contractor has

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!