Question: Earned Value Analysis A contractor has established the following earned value figures for concrete work: $ 2 . 1 0 ? sf of formwork $
Earned Value Analysis
A contractor has established the following earned value figures for concrete work:
$ sf of formwork
$ cy of concrete placed
$ of rebar set
The contractor is evaluating a subnetwork consisting of his concrete operations as part of a larger
project. The subnetwork contains forming, rebar setting, and concrete and curing activities.
Forming and rebar are estimated to take weeks overall followed by week for concrete and
cure activities. Estimated quantities are sf of formwork, lbs of rebar and of
concrete.
Three weeks have passed since the start of this subnetwork. The following weekly report
provides the job status.
Analyze the status of this subnetwork regarding budget and schedule.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
