Question: Earned Value Management (EVM) Assignment Problems 1. Using the information below, calculated the figures in the table and describe what the results of each calculation
Earned Value Management (EVM) Assignment Problems 1. Using the information below, calculated the figures in the table and describe what the results of each calculation mean to you as a project manager. What do you propose to do? PV= $25,000 EV= $30,000 AC= $29,000 BAC = $100,000 Term Calculation Answer Interpretation Schedule variance (SV) Cost variance (CV) Schedule performance index (SPI) Cost performance index (CPI) Estimate to complete (ETC) Estimate at completion (EAC) To-complete performance index (TCPI)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
