Question: Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly ) and progress in an objective manner in terms

Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value). The data identified below was listed in the projects status report:

Planned Value of work (PV) = $70,000

Earned Value of work performed (EV) = $50,000

Actual Cost of work performed (AC) = $75,000

Original Planning:

Budgeted cost At Completion (BAC) = $100,000

Original length of the project is 15 months

Using the data, calculate the following:

a). Cost Performance Index (CPI). (2 marks)

b). Schedule Performance Index (SPI). (2 marks)

c). Expected cost At Completion (EAC). (2 marks)

d). The money needed from the time of the report to complete the project i.e., Estimate at Completion (ETC). (2 marks)

e). The Schedule Variance (SV). (2 marks)

f). Discuss how the project is tracking. (5 marks)

Answer a) to f) below:

THE QUESTION IS OF ICT204 PROJECT MANAGEMENT SUBJECT.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!