Question: Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly ) and progress in an objective manner in terms
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value). The data identified below was listed in the projects status report:
Planned Value of work (PV) = $70,000
Earned Value of work performed (EV) = $50,000
Actual Cost of work performed (AC) = $75,000
Original Planning:
Budgeted cost At Completion (BAC) = $100,000
Original length of the project is 15 months
Using the data, calculate the following:
a). Cost Performance Index (CPI). (2 marks)
b). Schedule Performance Index (SPI). (2 marks)
c). Expected cost At Completion (EAC). (2 marks)
d). The money needed from the time of the report to complete the project i.e., Estimate at Completion (ETC). (2 marks)
e). The Schedule Variance (SV). (2 marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
