Question: Earned Value Management (EVM3) You are working on a project that is scheduled to be completed in 10 months . The total budget for the
Earned Value Management (EVM3)
You are working on a project that is scheduled to be completed in 10 months. The total budget for the project is $10,000. Six months have passed and the schedule indicates that 60% of the work should be completed by now. But your team has only completed 50% of the project and spent $8,000.
What is the Actual Cost (AC) for this project at this point in time?
What is the Actual Cost (AC) for this project at this point in time?
$8000
$5000
$6000
$10,000
Question at position 37
37
2 points
Question 37 is unpinned. Click to pin.
Question at position 37
What is the Earned Value (EV) for this project at this point in time?
What is the Earned Value (EV) for this project at this point in time?
$10,000 * 50% = $5,000
$8,000 * 50% = $4,000
$10,000 * 60% = $6,000
$6,000 * 50% = $3,000
Question at position 38
38
2 points
Question 38 is unpinned. Click to pin.
View Stimulus
Question at position 38
What is the BAC at this point?
What is the BAC at this point?
$6000
$7000
$5000
$8000
$10,000
Question at position 39
39
2 points
Question 39 is unpinned. Click to pin.
View Stimulus
Question at position 39
What is the SPI at this point?
What is the SPI at this point?
0.60
0.8333
0.75
0.625
Question at position 40
40
2 points
Question 40 is unpinned. Click to pin.
View Stimulus
Question at position 40
What percentage is the project behind schedule? [Hint: SV%)
What percentage is the project behind schedule? [Hint: SV%)
None of the above
62.5%
60%
16%
Question at position 41
41
2 points
Question 41 is unpinned. Click to pin.
View Stimulus
Question at position 41
What percentage is the project over budget at this time? [Hint:CV%]
What percentage is the project over budget at this time? [Hint:CV%]
30%
37.5%
60%
50%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
