Question: Earned value management involves calculating three values for each activity or summary activity from the project's WBS: 1 The planned value ( PV ) is

Earned value management involves calculating three values for each activity or summary activity from the project's WBS:
1 The planned value (PV) is the authorized budget assigned to scheduled work. Suppose that a project included a summary
activity of purchasing and installing a new web server. Suppose further that, according to the plan, it would take one week
and cost a total of $10,000 for the labor hours, hardware, and software.
2 The actual cost (AC) is the realized cost incurred for the work performed on a activity during a specific time period. For
example, suppose that it actually took two weeks and cost $20,000 to purchase and install the new web server. Assume that
$15,000 of these actual costs were incurred during week 1 and $5,000 was incurred during week 2
3 The earned value (EV) is the measure of work performed expressed in terms of the budget authorized for that work. It cannot
be greater than the authorized PV budget for a component as it is calculated as the sum of the PV of the completed work.
Based on the assumptions above, please list the earned value calculations for on activity after week 1.
Activity Week 1
1 Earned Value (EV)
2 Planned value (PV)
3 Actual cost (AC)
4 Cost variance (CV)
5 Schedule variance (SV)
6 Cost performance index (CPI)
7 Schedule performance index (SPI)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!