Question: Earned value management involves calculating three values for each activity or summary activity from the project's WBS: 1 The planned value ( PV ) is
Earned value management involves calculating three values for each activity or summary activity from the project's WBS:
The planned value PV is the authorized budget assigned to scheduled work. Suppose that a project included a summary
activity of purchasing and installing a new web server. Suppose further that, according to the plan, it would take one week
and cost a total of $ for the labor hours, hardware, and software.
The actual cost AC is the realized cost incurred for the work performed on a activity during a specific time period. For
example, suppose that it actually took two weeks and cost $ to purchase and install the new web server. Assume that
$ of these actual costs were incurred during week and $ was incurred during week
The earned value EV is the measure of work performed expressed in terms of the budget authorized for that work. It cannot
be greater than the authorized PV budget for a component as it is calculated as the sum of the PV of the completed work.
Based on the assumptions above, please list the earned value calculations for on activity after week
Activity Week
Earned Value EV
Planned value PV
Actual cost AC
Cost variance CV
Schedule variance SV
Cost performance index CPI
Schedule performance index SPI
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
