Question: Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 Pour foundation April 1 $50,000 May
Earned-value analysis. A project budget calls for the following expenditures:
| Task | Date | Budgeted Amount |
| Build forms | April 1 | $10,000 |
| Pour foundation | April 1 | $50,000 |
| May 1 | $100,000 | |
| Frame walls | May 1 | $30,000 |
| June 1 | $30,000 | |
| Remaining tasks | July 1 and beyond | $500,000 |
Define each term in your own words, calculate these values for the above project, and show your work:
DATA:
2. Budget at Completion (BAC) is the sum of the total cost or expenditure that is allotted to the individual phase of the projects. The BAC for the given project is $720000.
3. Planned Value is the approved value of the work to be completed in a given time.
Planned value = % of work to be completed on given date X budget at completion
On 1 May the 20% of project is estimated to be completed. Hence
PV = 20%*720000 = 144000
4. Earned Value is the work actually completed to date.
EV = % work completed X Total budget expenditure.
At 1 May the total budget expenditure is $160000 but the foundation work is only 2/3rd complete. So
EV = 10000+(150000*2/3) = 10000+10000= $20000
Question:
- SV as of May 1.
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
- Schedule performance index (SPI)
- Cost performance index (CPI)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
