Management of Mittel Company would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:
Inspection time0.3daysWait time (from order to start of production)15.5daysProcess time3.3daysMove time0.9daysQueue time4.2days
Required:
Compute the throughput time.
Note: Round your answer to 1 decimal place.
Compute the manufacturing cycle efficiency (MCE) for the quarter.
Note: Round your percentage answer to nearest whole percent.
What percentage of the throughput time was spent in nonvalue-added activities?
Note: Round your percentage answer to nearest whole percent.
Compute the delivery cycle time.
Note: Round your intermediate calculations and final answer to 1 decimal place.
If by using Lean Production all queue time during production is eliminated, what will be the new MCE?
Note: Do not round intermediate calculations. Round your percentage answer to 1 decimal place.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!