Question: eBook Check my workCheck My Work button is now enabled1 Item9 Item 9 Fogerty Company makes two productstitanium Hubs and Sprockets. Data regarding the two
eBook
Check my workCheck My Work button is now enabled1
Item9
Item 9
Fogerty Company makes two productstitanium Hubs and Sprockets. Data regarding the two products follow:
| Direct Labor-Hours per Unit | Annual Production | ||
| Hubs | 0.80 | 25,000 | units |
| Sprockets | 0.40 | 42,000 | units |
Additional information about the company follows:
-
Hubs require $25 in direct materials per unit, and Sprockets require $18.
-
The direct labor wage rate is $18 per hour.
-
Hubs require special equipment and are more complex to manufacture than Sprockets.
-
The ABC system has the following activity cost pools:
| Estimated | Activity | ||||
| Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
| Machine setups (number of setups) | $ | 16,065 | 85 | 68 | 153 |
| Special processing (machine-hours) | $ | 253,000 | 4,600 | 0 | 4,600 |
| General factory (organization-sustaining) | $ | 288,800 | NA | NA | NA |
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.