Question: eBook Question Content Area Lead Time Analysis Fuzzy Pals Inc. manufactures toy stuffed animals. The direct labor time required to cut, sew, and stuff a

eBook
Question Content Area
Lead TimeAnalysis
Fuzzy Pals Inc. manufactures toy stuffed animals. The direct labor time required to cut, sew, and stuff a toy is 8 minutes per unit. The company makes two types of stuffed toysa lion and a bear. The lion is assembled in lot sizes of 40 units per batch, while the bear is assembled in lot sizes of 10 units per batch. Since each product has direct labor time of 8 minutes per unit, management has determined that the lead time for each product is 8 minutes.
a.Lead time includes ___,___, and ___.
a. Value-added time, wait time and other non-value-added time.
b. Production time, packing time and value-added time.
c. Idle time, direct labor hours, and wait time.
d. None of the above.
abcd
b.A toy manufacturing unit produces two types of products and the labor time for each product is 10 minutes. The batch size of product A is 40 units and batch size of product B is 8 units. The company considers the lead time of the products to be equal to the labor hours. Is this decision correct? Support your answer by selecting the reason.
a. Yes
b. No
ab
Reason:
a. Lead time of the product includes value-added time, idle time and other non-value-added time.
b. Labor time and lead time adds value to the product.
c. Lead time and labor time are one and the same with different names.
d. None of the above.
abcd

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!