Construction of a building is based on the following CPM network:
Activity Predecessor Successor Normal
Time Normal
Cost Crash
Time Crash
Cost
A B C D $ $
B A E
C B A F
D A F G
E B G
F C D G
G E F D
Draw the network and answer the following questions.
a What are the normal project completion time and normal cost?