Construction of a building is based on the following CPM network:
Activity Predecessor Successor Normal
Time Normal
Cost Crash
Time Crash
Cost
A B, C, D 6 $ 1002 $ 150
B A E 8802140
C B, A F 240160
D A F, G 3802120
E B G 5803140
F C, D G 5601100
G E, F, D 61202160
Draw the network and answer the following questions.
a. What are the normal project completion time and normal cost?