Question: Eddie's Embroidery makes a jacket that should take 1.5 direct labor hours at $16.00 per hour. In April, 2,000 jackets were made that required 3,150

Eddie's Embroidery makes a jacket that should take 1.5 direct labor hours at $16.00 per hour. In April, 2,000 jackets were made that required 3,150 direct labor hours. Eddie's actual payroll during April was $49,140. What is the labor quantity variance? 0 $1,140 U 0 $2,400 U O $2,400 F 0 $1,260 F