Question: education.com/ext/map/index.html?_con=con&externweer=0&launchUrl=https%253A%252Backboard.com%252Fwebapps/6252Fportala MY DIME- Google Drive Ege Watching and Digital X other amework Saved Mickley Company's plantwide predetermined overhead rate is $24.00 per direct labor hour
education.com/ext/map/index.html?_con=con&externweer=0&launchUrl=https%253A%252Backboard.com%252Fwebapps/6252Fportala MY DIME- Google Drive Ege Watching and Digital X other amework Saved Mickley Company's plantwide predetermined overhead rate is $24.00 per direct labor hour and its direct labor wage rate is $16.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 210 $ 160 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 90 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1 Total manufacturing cost 2. Unit product cost por unit