Question: Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the project's MIRR? WACC: 9.00% Year:0,1,2,3 Cash
Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the project's MIRR?
WACC: 9.00%
Year:0,1,2,3
Cash flows: -$1,000, $450, $450, $450