Question: Eight activities, A , B , C , D , E , F , G and H , must be completed for a project. The

Eight activities, A,B,C,D,E,F,G and H, must be completed for a project.
The network above shows these activities and their usual duration in hours.
The duration of each activity can be reduced by one hour.
To complete this project in 16 hours, the minimum number of activities that must be reduced by one hour
each is
A.1
B.2
C.3
D.4
 Eight activities, A,B,C,D,E,F,G and H, must be completed for a project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock