Question: Eight jobs are to be processed through a two - machine flow shop. The first operation involves production and the second involves painting. Determine a

Eight jobs are to be processed through a two-machine flow shop. The first operation involves
production and the second involves painting. Determine a sequence that will minimize the total
completion time for this group of jobs. Processing times are as follows:
Processing Time (hours)
Job | Work Center 1| Work Center 2
A 510
B 78
C 32
D 1018
E 139
F 116
G 1517
H 41
(