Question: electric bike Work breakdown structure (WBS) divides the project into recognisable tasks and activities at different levels - Level 1: Project 25-Sep-20 6 - Level
Generate a Work Breakdown Structure (WBS) for your project, similar to the example shown below 1.0 Trailer Design and Production 1.1 1.3 Project Planning 1.2 Project Development Project Close 1.2.1 1.1.1 Define design requirements 1.1.2 Select bought in components Frame Design 1.2.2 Trailer Design 1.2.3 Assemble &Test 1.3.1 Set up production line 1.3.2 Build 1st off batch 1.2.1.1 1.2.1.2 1.2.2.1 Design Lab Test Compete frame frame trailer geometry geometry design 1.2.3.1 1.2.3.21 1.2.3.3 Field Assemble Lab Test trial prototype prototype prototype A WBS of Trailer Design and Production 25-Sep-20 7
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
