Question: Element 2 standard time is 1.097. Need Element 1 and 3 Problem 7-10 The data in the table below represent time study observations for a

Element 2 standard time is 1.097. Need Element 1 and 3
Problem 7-10 The data in the table below represent time study observations for a woodworking operation. (Hint. See Solved Problems section.) Element Performance Rating 110% 115 105 OBSERVATIONS (minutes per cycle) 1 2 3 4 5 6 1.20 1.17 1.16 1.22 1.24 1.15 0.83 0.87 0.78 0.82 0.85 1.32* 0.58 0.53 0.52 0.59 0.60 0.54 *Unusual delay, disregard time. a. Based on the observations, determine the standard time for the operation, assuming an allowance of 15 percent of job time. (Round your intermediate calculations and final answers to 3 decimal places.) Element Standard time 1.097 N wStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock