Question: Emerson Enterprises is constructing a building. Construction began in 2022, and the building was completed on December 31, 2022. Emerson made payments to the

Emerson Enterprises is constructing a building. Construction began in 2022, and the

Emerson Enterprises is constructing a building. Construction began in 2022, and the building was completed on December 31, 2022. Emerson made payments to the construction company of $500,000 on July 1, $1,500,000 on September 1, and $2,000,000 on December 31. What is the amount of weighted - average accumulated expenditures that provides the basis for determining capitalized interest? OA. $916,667 OB. $1,000,000 OC. $750,000 OD. $1,333,333