Question: Enabled: ACCT2020 Exam #1: Ch. i Saved Help Save & Exit S Washington, Inc. produces two different products (Product C and Product 2) using two


Enabled: ACCT2020 Exam #1: Ch. i Saved Help Save & Exit S Washington, Inc. produces two different products (Product C and Product 2) using two different activities: Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The cost of Machining is $750,000, while the cost of Inspection is $90,000. The activity drivers are used as follows: Product C Product 2 Total -53 Machine hours 1,000 3, 000 4,000 Number of batches 45 15 60 What is the activity rate for Machining? Multiple Choice O $5750.00 per machine hour